SBA/HUBZone Certified

Venezia Construction, Inc.     CA License No: 851390

 

HomeProjectsReferencesContact UsRequest for Estimate

 NASA-Ames Building 15 Office Upgrade
 The Building 15 office upgrade included the following tasks:
 
1.      Removing existing partitions
·         Salvaging/disposing of partitions as appropriate
2.      Framing new walls and doors
3.      Designing and constructing tube-steel frames (for glass wall blocks)
4.      Constructing new walls and installing doors and installing glass wall blocks.
5.      Installing new electrical conduit.
6.      Installing new communication wires.
7.      Installing lighting.
8.      Patching and painting of new construction to match existing.
 
The project was completed ahead of schedule and on budget. Project was recognized by office occupants for quality of work, timely completion and minimized impact on staff’s work obligations. 

 NASA Ames Building 18
 
Building Renovation & Modification
 Building 18 required significant renovations and modifications to bring the facility up to federal, state and local regulations and building codes and to make the building ready for occupancy.    The scope of this project included the following tasks:
 
1.      Oversee architectural plans and obtain all necessary permits.
2.      Install fire suppressions system and fire alarms, including upgrading electrical power distribution systems.
3.      Install new ADA accessible doorways, exit ramp and emergency exit lights.
4.      Enclose third floor stairwell.
5.      Provide interior floor treatments and painting. 
 
The project was completed ahead of schedule and on budget. Project was recognized by office occupants for quality of work and timely completion.
 

 
NASA-Ames
Building 234
Office Renovation
Building 234 office renovation project included the following tasks:
 
1.      Remove existing flooring
·         Remove and dispose all existing rubber-based flooring and existing carpeting per all federal, state and local environmental protection and health standards.
2.      Install new flooring
·         Prepare sub-flooring.
·         Supply and install approximately 350 yards of carpeting and 4,000 yards of tile, and 2,500 linear feet of base cover.
3.      Patch and paint multiple offices and public access areas.
4.      Work was staggered to minimize impact on office occupants’ productivity.
 
The project was completed ahead of schedule and on budget. Project was recognized by office occupants for quality of work, timely completion and minimized impact on staff’s work obligations.
 

 NASA Ames Building 19
Lighting Standard Installation and Landscaping.
 The Building 19 visitors’ quarters’ parking lot required the installation of adequate parking lot lighting standards.   In addition, the contract included installing an irrigation system and upgrading the landscaping. The scope of this project included the following tasks:
 
1.      Install 6 lighting standards, per specifications, including all electrical wiring and power distribution.
2.      Install new irrigation system, per supplied specifications.
3.      Landscape designated area.
 
The project was completed ahead of schedule.
 

 NASA Ames Building N255
Restroom Remodel
 The restrooms in NASA Building N255 were non-compliant with health and safety standard requirements. The scope of this project included the following tasks:
 
1.      Removal, demolition and disposal of flooring, partitions, plumbing fixtures and piping.
2.      Installing cultured marble wainscoting from floor to ceiling.
3.      Install new flooring, partitions, plumbing and lighting fixtures.
4.      Install new cultured marble sinks and cabinetry.
 
The project was completed ahead of schedule and on budget. Project was recognized by office occupants for quality of work and timely completion. 

 NASA Ames Building 203
 
Building Modification
Remodeling the old photo lab into office spaces requires performing abatement and ensuring all facility systems are compliant with federal, state and local codes and regulations. The scope of this project included the following tasks:
 
1.      Remove sheetrock over existing windows, install new doors and walls.
2.      Cap off plumbing old photo lab plumbing no longer necessary for office area.
3.      Perform all necessary abatement.
4.      Install additional lighting as necessary.
5.      Paint interior walls.
 
This project initiated December, 2004 and was completed in January, 2005.